Fayettevilleโ€™s yearsโ€‘delayed Fire Station 4 will be torn down and rebuilt from scratch after the city council voted Monday to accept a consultantโ€™s recommendation that the structure is too compromised to salvage.

The decision follows a 57โ€‘page report from Applied Building Sciences (ABS) that documented extensive construction failures at the Bragg Boulevard site and placed sole responsibility on the projectโ€™s former contractor, W.B. Brawley Co. The city terminated the Wilmingtonโ€‘based firm in late 2024 and is now locked in dueling lawsuits over who is to blame for the projectโ€™s collapse.

Steve Moore, who directs ABSโ€™ Charlotte office, delivered the findings to council members during their meeting on Monday. He told them the buildingโ€™s defects were so severe and intertwined that repairing the structure was not a safe or reliable option.

โ€œIn over 17 years of work in this area, I have never recommended that a partially constructed building be torn down,โ€ Moore said. โ€œHowever, it is our opinion that the extent, severity, complexity of potential reviews of the identified constructionโ€‘related issues warrants this recommendation and implies ABSโ€™ serious concerns about this building.โ€

Council member Deno Hondros pressed Moore on whether the station could be safely repaired.

Mooreโ€™s answer was unequivocal: no.

โ€œThereโ€™s too many unknowns,โ€ he said. โ€œOur concern is providing a building to the city that provides guaranteed longโ€‘term success.โ€

ABSโ€™ formal recommendation states: โ€œThe existing building be completely demolished, including the superstructure, foundations, and remaining systems that are installed to allow for reconstruction of the building.โ€

Council members unanimously voted to accept ABSโ€™ recommendation and directed city staff to return with options for demolition, reconstruction, cost estimates, and a timeline.

A section of the unfinished roof at Fire Station 4 shows deteriorated materials and gaps in the assembly, one of several structural failures identified by Applied Building Sciences in its report to the city. Credit: Courtesy of Applied Building Sciences

Transparency Debate Erupts 

Before the meeting, the council met in closed session to discuss the cityโ€™s lawsuit against Brawley. That secrecy drew criticism from Council member Shaun McMillan, who said the public deserves a fuller accounting of what went wrong.

McMillan took office in December. 

โ€œI would urge us to get things out of private session and out into the public,โ€ McMillan said. โ€œI think itโ€™s time to be transparent, fully transparent with the public about what has happened with this projectโ€ฆ not only whatโ€™s going wrong with this project, but how we get to success.โ€

Mayor Mitch Colvin pushed back, arguing that Mooreโ€™s detailed presentation already represented significant transparency.

โ€œI think him giving this detailed report on the good, bad, ugly, is as transparent as you can get,โ€ Colvin said.

McMillan replied: โ€œUnfortunately, thereโ€™s more.โ€

Construction on Fire Station 4 began in August 2022 and was supposed to be completed in 2023. Instead, work stalled in late 2024 after the city terminated its $9.4 million contract with Brawley. By then, Fayetteville had already spent $4.3 million.

The city sued Brawley on Sept. 15, 2024, alleging the contractorโ€™s โ€œmismanagementโ€ caused โ€œrepeated and nearly continuous delays.โ€ Brawley countersued weeks later, arguing the cityโ€”not the contractorโ€”breached the agreement by providing a flawed design, failing to pay properly, and denying justified time extensions.

The litigation is ongoing.

Brawley did not respond to a request for comment Thursday. In an earlier email to CityView, company president Jon Gore defended the firmโ€™s work and argued against demolition, saying โ€œtearing down the building would be a substantial waste of taxpayer funds and is woefully premature.โ€

Consultant Clears Architect, Inspectors, and City of Blame

Council member Derrick Thompson asked Moore to explain why ABS attributed the failures solely to the contractor and not to the projectโ€™s design or oversight.

Moore said the problems were rooted in execution, not design.

He listed multiple issues such as improper roof panel seams, unsupported insulation, unsealed roofโ€‘toโ€‘wall gaps, a concrete slab poured thinner than code requires, and plumbing installed with the wrong material.

โ€œThose things are 100% attributable to the contractor,โ€ he said. 

Moore also said Stewartโ€‘Cooperโ€‘Newell Architects, which visited the site monthly, and Froehling & Robertson, the specialโ€‘inspections firm, were not responsible for the failures. Their roles were limited, he said, and neither had authority over the contractorโ€™s daily work.

He added that the city manager, city attorney, fire chief, and other staff were not responsible for the construction problems. โ€œThey were certainly involved and monitored the project and took actions as needed and warranted,โ€ Moore said.

Council member Lynne Greene emphasized that the city did attempt to maintain oversight.

โ€œThere was a thirdโ€‘party oversight on this job,โ€ she said. โ€œThey met, they said โ€˜weโ€™ll fix it,โ€™โ€ she added, referring to the contractor. But once they would go back and review the work done by the contractor, they found it was not done right. โ€œIt was all kinds of crazy things.โ€

Council member Antonio Jones voiced sharper skepticism, questioning how the project advanced so far despite multiple inspections. โ€œItโ€™s difficult to understand how we reached this point with so many eyes on it,โ€ he said. โ€œThis new information only raises further questions.โ€

Thompson said the councilโ€™s priority now is ensuring firefighters are never put at risk by a compromised building.

โ€œWeโ€™re going to make sure we do everything that we keep our first responders,โ€ he said. He added that he did not want it โ€œto be on our conscienceโ€ if something went wrong years down the road.


Did you find this story useful or interesting? It was made possible by donations from readers like you to the News Foundation of Greater Fayetteville, a 501(c)(3) charitable organization committed to an informed democracy in Fayetteville and Cumberland County. Please consider making a tax-deductible donation so CityView can bring you more news and information like this.

Rachel Heimann Mercader was CityView's government reporter, covering the City of Fayetteville, from October 2025 to September 2026. She has reported in Memphis, the Bay Area in California, Naples, Florida, and Chicago, covering a wide range of stories that center community impact and institutional oversight.